C_TPLM22_67 · Question #2
Which version serves as a proof of the project status in the past and also serves as a comparison with the operative project? Please choose the correct answer. Response:
The correct answer is C. Project version. See the full explanation below for the reasoning.
Question
Which version serves as a proof of the project status in the past and also serves as a comparison with the operative project? Please choose the correct answer. Response:
Options
- AMilestone version
- BOperative version
- CProject version
- DSimulation version
How the community answered
(18 responses)- A17% (3)
- B6% (1)
- C72% (13)
- D6% (1)