SAP
C_TPLM22_67 · Question #10
In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as? Please choose the correct answer. Response:
The correct answer is A. Floats. See the full explanation below for the reasoning.
Question
In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as? Please choose the correct answer. Response:
Options
- AFloats
- BTime gaps
- CHigh priority
- DDeviations
How the community answered
(29 responses)- A86% (25)
- B3% (1)
- C3% (1)
- D7% (2)
Community Discussion
No community discussion yet for this question.