C_TPLM22_67 · Question #10

In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as? Please choose the correct answer. Response:

The correct answer is A. Floats. See the full explanation below for the reasoning.

Question

In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as? Please choose the correct answer. Response:

Options

  • AFloats
  • BTime gaps
  • CHigh priority
  • DDeviations

How the community answered

(29 responses)
  • A
    86% (25)
  • B
    3% (1)
  • C
    3% (1)
  • D
    7% (2)