C_TPLM22_67 · Question #11
In which transactions can you specify whether networks are scheduled together with maintenance orders that have been assigned as sub networks? There are 2 correct answers to this question. Response:
The correct answer is A. Project scheduling C. Overall network scheduling. See the full explanation below for the reasoning.
Question
In which transactions can you specify whether networks are scheduled together with maintenance orders that have been assigned as sub networks? There are 2 correct answers to this question. Response:
Options
- AProject scheduling
- BNetwork scheduling
- COverall network scheduling
- DForward scheduling
How the community answered
(64 responses)- A78% (50)
- B14% (9)
- D8% (5)