C_TPLM22_67 · Question #26
Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity? There are 3 correct answers to this question. Response:
The correct answer is B. Scheduling must have been carried C. A work center must be maintained in the activity D. A distribution key must be maintained in the work center. See the full explanation below for the reasoning.
Question
Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity? There are 3 correct answers to this question. Response:
Options
- AThe capacity requirements indicator must not be set in the network header
- BScheduling must have been carried
- CA work center must be maintained in the activity
- DA distribution key must be maintained in the work center
How the community answered
(43 responses)- A21% (9)
- B79% (34)