SAP
C_TPLM22_67 · Question #40
When using budgeting and active availability control, which business transactions affect the current budget? There are 3 correct answers to this question. Response:
The correct answer is A. Original budget C. Supplements D. Transfers. See the full explanation below for the reasoning.
Question
When using budgeting and active availability control, which business transactions affect the current budget? There are 3 correct answers to this question. Response:
Options
- AOriginal budget
- BRevenues
- CSupplements
- DTransfers
- ECost element planning
How the community answered
(26 responses)- A81% (21)
- B8% (2)
- E12% (3)
Community Discussion
No community discussion yet for this question.