SAP
C_TPLM22_67 · Question #44
Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and…
The correct answer is B. Project planning board. See the full explanation below for the reasoning.
Question
Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity? Please choose the correct answer. Response:
Options
- AWork center planning board
- BProject planning board
- CCapacity planning board
- DWorkforce planning board
How the community answered
(16 responses)- A13% (2)
- B81% (13)
- C6% (1)
Community Discussion
No community discussion yet for this question.