C_TPLM22_67 · Question #18
Which of the following combination of assignment to an externally-processed activity allows you to carry out capacity planning for your vendors? Please choose the correct answer. Response:
The correct answer is D. Work center and planned work. See the full explanation below for the reasoning.
Question
Which of the following combination of assignment to an externally-processed activity allows you to carry out capacity planning for your vendors? Please choose the correct answer. Response:
Options
- AWork center and vendor
- BWork center and activity
- CActivity and task
- DWork center and planned work
How the community answered
(29 responses)- A14% (4)
- B7% (2)
- C3% (1)
- D76% (22)