RCDD-002 Exam Questions
357 real RCDD-002 exam questions with expert-verified answers and explanations. Page 2 of 8.
- Question #51
During bidding the ICT distribution designer should review the bid responses for compliance and completeness. Afterwards, the designer should report the findings and recommendation...
- Question #52
An RFQ usually provides more detail than RFP in selection material such as
- Question #53
A system integration approach of a BAS on to a LAN can usually reduce the cost of cabling- related changes by
- Question #54
Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)
- Question #55
Which of the following team members is responsible for ensuring compliance with the contract documents (CD)?
- Question #56
In a design type Scope of Work (SoW) the ICT distribution designer is responsible for providing
- Question #57
The marketing department of a firm has tasked the organization to design a structured cabling system allowing them to support either 10GBaseT or HDBASE-T. The budget requires that...
- Question #58
What category/class of cabling does BICSI recommend for the MINIMUM performance level of horizontal balanced twisted-pair cabling?
- Question #59
Who prepares the submittals that are reviewed and approved to ensure that the client's design criteria is met in regards to material selection?
- Question #60
Which two of the following roles does an ICT distribution designer use to ensure a timely and cost-effective telecommunications construction project? (Choose two.)
- Question #61
A 3 trade size conduit is sized at
- Question #62
Which of the following options BEST describes Request for Quote (RFQ)?
- Question #63
Which of the following transmitter light sources has a MINIMUM bandwidth of 4700 MHz/km (EMB) at 850 nm">
- Question #64
A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting. As part of the designer's responsibilities, which two of the following...
- Question #65
An Ethernet passive optical network (EPON) uses an aggregation device called an optical line terminal (OLT). An OLT can support a MINIMUM of______subscribers per port using a passi...
- Question #66
What is the RECOMMENDED bend radius of a conduit with an internal diameter of 51 mm (2 in)?
- Question #67
Using a vertical cable support structure can create issues for the cable attached to the pathway Several issues can result It the support work is not clone correctly. Which two of...
- Question #68
The MINIMUM required for backbone floor to floor pathways is five (5) sleeves each being 103 mm (four trade size) in diameter. What increase in usable floor space should another 10...
- Question #69
An ICT distribution designer is reviewing a client's site information (spaces and pathways) to determine network technology and equipment selection. This is referred to as a_______...
- Question #70
Which stakeholder of a project team is responsible to provide closeout documentation to the client?
- Question #71
The size and number of conduits or sleeves used for backbone pathways depend on the usable floor space served by the backbone distribution system. What is the MINIMUM trade size of...
- Question #72
Which two of the following are means in which radiated interference primarily enters electronic devices? (Select two options.)
- Question #73
What step can be a phase of the Bidding and Negotiating process?
- Question #74
How many classes of telecommunications administration are there?
- Question #75
For a cost estimate, an ICT distribution designer should produce a document listing each task with a cost placed beside them. The type of document used is a
- Question #76
Based on the estimated work area size, what is the MAXIMUM number of work areas that a telecommunications enclosure shall serve?
- Question #77
Which two of the following are included in the ICT distribution designer's role of vendor and contractor coordination'? (Select two options.)
- Question #78
Which of the following terms is often used to describe two parallel paths that have identical conductive terminations to two separate grounding reference points?
- Question #79
Which two of the following may the ICT distribution designer need to provide in order to identify the BEST solutions for the client's need? (Select two options.)
- Question #80
When designing for horizontal pathways in an environment that requires fire-stopping for penetrating a rated wall, what is the MAXIMUM till ratio for telecommunications cabling in...
- Question #81
In a contiguous properly environment (e. g., where campus backbone cables exist), which two of the following are CRITICAL factors to understand for maintenance and growth purposes?...
- Question #82
ICT project installation issues that require coordination with mechanical, electrical and/or other "trades" can be BEST accomplished by
- Question #83
For the MAXIMUM flexibility of a cabling system in a hierarchical star topology, ALL backbone cables and links to ER's should be terminated at the
- Question #84
Which of the following two items are examples of items associated with a submittal? (Select two options.)
- Question #85
Which two of the following are ADVANTAGES of aerial pathways? (Select two options.)
- Question #86
Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? (Select two options.)
- Question #87
When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following action...
- Question #88
A large international manufacturing company is centralizing its IT which is currently spread over 16 countries. The transition means physically regrouping the infrastructure and al...
- Question #89
To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The pro...
- Question #90
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedul...
- Question #91
A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?
- Question #92
A program manager has a multiple-project program that is scheduled to be completed by year's end. During the program delivery phases of the protects several mandatory changes are i...
- Question #93
A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase. Trackin...
- Question #94
A program manager concurrently implements a software program at four client locations. The client's objective is to maintain quality while shortening the software implementation ti...
- Question #95
An R&D group director approves a major program's charter although the director has a high level of understanding of the program's scope (hoy are unsure of how the program manager c...
- Question #96
A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?
- Question #97
During program execution, a program manager receives feedback from an executive sponsor (hat some program stakeholders may not understand the intended benefits of the program. Whic...
- Question #98
During a program's definition phase, it is determined that the best approach for delivering the programs intended benefits is to supplement corporate resources with the procurement...
- Question #99
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives. How should the program manager demonstrate the...
- Question #100
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager revi...