The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program…

The correct answer is C. Resource interdependency management. See the full explanation below for the reasoning.

Question

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B. This is an example of which of the following?

Options

  • AProgram resource management planning
  • BProgram risk mitigation
  • CResource interdependency management
  • DProject resource planning

How the community answered

(40 responses)
  • A
    15% (6)
  • B
    5% (2)
  • C
    73% (29)
  • D
    8% (3)