The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program…
The correct answer is C. Resource interdependency management. See the full explanation below for the reasoning.
Question
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B. This is an example of which of the following?
Options
- AProgram resource management planning
- BProgram risk mitigation
- CResource interdependency management
- DProject resource planning
How the community answered
(40 responses)- A15% (6)
- B5% (2)
- C73% (29)
- D8% (3)