RCDD-002 · Question #101

Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while…

The correct answer is A. Review the issue with the program management office (PMO) to determine which template to use. Option A is correct because the PMO is the authoritative body for organizational standards, including templates, processes, and tools - resolving template disputes falls squarely within its mandate, and the PMO's decision ensures alignment with enterprise-wide governance rather…

ICT Design Fundamentals and Project Management

Question

Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while others prefer another. How should the program manager decide which template is appropriate?

Options

  • AReview the issue with the program management office (PMO) to determine which template to use
  • BReview the issue with the project managers and come to mutual agreement on which template to
  • CMeet with the program governance board to select an appropriate template
  • DAllow the component project managers to use their preferred templates

How the community answered

(34 responses)
  • A
    74% (25)
  • B
    6% (2)
  • C
    6% (2)
  • D
    15% (5)

Explanation

Option A is correct because the PMO is the authoritative body for organizational standards, including templates, processes, and tools - resolving template disputes falls squarely within its mandate, and the PMO's decision ensures alignment with enterprise-wide governance rather than local preferences.

Why the distractors are wrong:

  • B is tempting but wrong: mutual agreement among the project managers may produce a locally acceptable choice that still violates organizational standards; consensus doesn't equal compliance.
  • C is wrong because the program governance board handles strategic decisions, risks, and benefits realization - not operational details like report formats.
  • D is wrong because allowing inconsistent templates undermines the program manager's ability to aggregate and compare status across component projects, defeating the purpose of program-level oversight.

Memory tip: When an exam question involves "which standard/template/process applies," default to the PMO - it's the keeper of organizational standards. If the question involves strategic program direction or go/no-go decisions, then think governance board.

Topics

#Program Management#Standardization#PMO Governance#Template Management