RCDD-002 · Question #70
Which stakeholder of a project team is responsible to provide closeout documentation to the client?
The correct answer is D. ICT Distribution Designer/Project Manager. Option D is correct because the ICT Distribution Designer/Project Manager holds end-to-end accountability for the project lifecycle, which explicitly includes compiling and delivering closeout documentation - warranties, as-built drawings, O&M manuals, and final reports - to…
Question
Which stakeholder of a project team is responsible to provide closeout documentation to the client?
Options
- AArchitect
- BHaving Jurisdiction (AHJ)
- CConstruction Manager
- DICT Distribution Designer/Project Manager
How the community answered
(39 responses)- A3% (1)
- B13% (5)
- C8% (3)
- D77% (30)
Explanation
Option D is correct because the ICT Distribution Designer/Project Manager holds end-to-end accountability for the project lifecycle, which explicitly includes compiling and delivering closeout documentation - warranties, as-built drawings, O&M manuals, and final reports - to the client upon project completion.
- A (Architect) contributes design documents and may review submittals, but their primary deliverable is the design, not the administrative closeout package handed to the client.
- B (AHJ) is a regulatory authority that receives permit applications and issues approvals/certificates; they're an external authority, not a project team member responsible for client deliverables.
- C (Construction Manager) oversees on-site construction execution and may gather field documents, but the PM/Designer role is the designated point of contact accountable for final documentation delivery to the client.
Memory tip: Think of the Project Manager as the "bookend" role - they start the project with the contract and close it with the closeout docs. The word "closeout" literally maps to the PM's job of closing out the project.