RCDD-002 · Question #79

Which two of the following may the ICT distribution designer need to provide in order to identify the BEST solutions for the client's need? (Select two options.)

The correct answer is A. Preliminary budget numbers E. Time constraints and/or milestones. Preliminary budget numbers (A) and time constraints/milestones (E) are correct because identifying the best solution requires understanding the two most fundamental project constraints - what the client can afford and when it must be delivered. Without these, a designer might…

ICT Design Fundamentals and Project Management

Question

Which two of the following may the ICT distribution designer need to provide in order to identify the BEST solutions for the client's need? (Select two options.)

Options

  • APreliminary budget numbers
  • BColor scheme for dropcables
  • CDocumentation plan
  • DRecommendations for label design of outlets
  • ETime constraints and/or milestones

How the community answered

(26 responses)
  • A
    73% (19)
  • B
    15% (4)
  • C
    4% (1)
  • D
    8% (2)

Explanation

Preliminary budget numbers (A) and time constraints/milestones (E) are correct because identifying the best solution requires understanding the two most fundamental project constraints - what the client can afford and when it must be delivered. Without these, a designer might recommend technically superior solutions that are either too expensive or impossible to implement within the required timeframe.

Why the distractors are wrong:

  • B (Color scheme for dropcables): An aesthetic implementation detail determined after a solution is chosen, not before.
  • C (Documentation plan): Addresses record-keeping and handoff processes, not solution selection criteria.
  • D (Label design of outlets): A granular finishing detail irrelevant to evaluating which solution best fits the client's needs.

Memory tip: Think of the classic project management triangle - scope, cost, and time. The two correct answers map directly to cost (budget) and time (milestones). When a question asks what's needed to find the "best" solution, anchor on constraints that determine feasibility, not cosmetic or administrative details.

Topics

#Design inputs and requirements#Budget and timeline constraints#Solution identification#Project planning