RCDD-002 · Question #86
Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? (Select two options.)
The correct answer is A. Test reports B. Shop drawings. In communications construction projects, Test Reports (A) and Shop Drawings (B) are the two submittals that contractors must formally submit for engineer/owner review and approval because they directly verify that installed systems meet design specifications and that…
Question
Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? (Select two options.)
Options
- ATest reports
- BShop drawings
- CCost summary
- DSite survey
- ERequest for information (RFI)
How the community answered
(57 responses)- A77% (44)
- C12% (7)
- D4% (2)
- E7% (4)
Explanation
In communications construction projects, Test Reports (A) and Shop Drawings (B) are the two submittals that contractors must formally submit for engineer/owner review and approval because they directly verify that installed systems meet design specifications and that equipment/materials conform to the approved design intent.
Why the distractors are wrong:
- C. Cost summary - a financial document used internally or for billing; it's not a technical submittal requiring design approval.
- D. Site survey - typically performed before or during design by the engineer, not a contractor submittal for approval.
- E. RFI - a request for clarification, not a document submitted for approval; it's a communication tool, not a formal submittal.
Memory tip: Think "SA" - Shop drawings show what will be installed, Assurance (test reports) prove it works. Both touch the physical system and must be verified by the engineer of record before and after installation, making them the two required approval submittals.
Topics