The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?

Options

  • AContact the project sponsors to present the details, impacts, and possible corrective actions
  • BGather all the details, analyze impacts, determine corrective actions and present the findings to
  • CWork with program sponsor to compile impact analysis data to obtain additional funding for the
  • DAsk the program team to compile all details, analyze impacts, determine corrective actions and