Question
The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?
Options
- AContact the project sponsors to present the details, impacts, and possible corrective actions
- BGather all the details, analyze impacts, determine corrective actions and present the findings to
- CWork with program sponsor to compile impact analysis data to obtain additional funding for the
- DAsk the program team to compile all details, analyze impacts, determine corrective actions and