Question

A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?

Options

  • AProgram sponsor
  • BCommunications manager
  • CProject manager
  • DProgram manager