What is the recommended MINIMUM setback for dirt (spoil) piles from the edge of an excavation (trench, pit, etc.)?

The correct answer is C. 610 mm (24 in). See the full explanation below for the reasoning.

Question

What is the recommended MINIMUM setback for dirt (spoil) piles from the edge of an excavation (trench, pit, etc.)?

Options

  • A305 mm (12 in)
  • B457 mm (18 in)
  • C610 mm (24 in)
  • D1 m (39 in)
  • E1.20 m (42 in)

How the community answered

(27 responses)
  • B
    4% (1)
  • C
    81% (22)
  • D
    11% (3)
  • E
    4% (1)