nerdexam
BICSI

RCDD-002 · Question #90

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited…

The correct answer is D. Conduct a stakeholder meeting to allow everyone to state their priorities. See the full explanation below for the reasoning.

Question

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits. Which of the following actions should the program manager take?

Options

  • AFocus on the internal stakeholders to ensure cost and) schedule objectives are achieved
  • BBalance stakeholder needs through the use of trade-offs among the stakeholder groups
  • CFocus on the external stakeholders to ensure the intended benefits are achieved
  • DConduct a stakeholder meeting to allow everyone to state their priorities

How the community answered

(24 responses)
  • A
    13% (3)
  • B
    8% (2)
  • C
    4% (1)
  • D
    75% (18)

Community Discussion

No community discussion yet for this question.

Full RCDD-002 Practice