RCDD-002 · Question #90
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited…
The correct answer is D. Conduct a stakeholder meeting to allow everyone to state their priorities. See the full explanation below for the reasoning.
Question
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits. Which of the following actions should the program manager take?
Options
- AFocus on the internal stakeholders to ensure cost and) schedule objectives are achieved
- BBalance stakeholder needs through the use of trade-offs among the stakeholder groups
- CFocus on the external stakeholders to ensure the intended benefits are achieved
- DConduct a stakeholder meeting to allow everyone to state their priorities
How the community answered
(24 responses)- A13% (3)
- B8% (2)
- C4% (1)
- D75% (18)