A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?
The correct answer is A. Request permission from the program governance board to initiate program closure activities. See the full explanation below for the reasoning.
Question
A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?
Options
- ARequest permission from the program governance board to initiate program closure activities
- BPresent additional opportunities to the program sponsor
- CApply the remaining budget to operational activities
- DApply the remaining budget to deferred enhancement requests
How the community answered
(34 responses)- A71% (24)
- B3% (1)
- C18% (6)
- D9% (3)