During a program's definition phase, it is determined that the best approach for delivering the programs intended benefits is to supplement corporate resources with the procurement of specific…

The correct answer is A. Make of buy decisions, alternatives analyses approach to competition, and best mix of contract. See the full explanation below for the reasoning.

Question

During a program's definition phase, it is determined that the best approach for delivering the programs intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers. The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?

Options

  • AMake of buy decisions, alternatives analyses approach to competition, and best mix of contract
  • BRequests for proposals (RFPs), proposal evaluation criteria, contract management and best mix
  • CRFPs. alternatives analyses, approach to competition, and requests for quotes (RFQs)
  • DMake-or-buy decisions, proposal evaluation criteria contract management, and RFQs

How the community answered

(36 responses)
  • A
    75% (27)
  • B
    17% (6)
  • C
    3% (1)
  • D
    6% (2)