RCDD-002 · Question #82
ICT project installation issues that require coordination with mechanical, electrical and/or other "trades" can be BEST accomplished by
The correct answer is B. issuing an RFI to the General/Prime Contractor. Issuing an RFI (Request for Information) to the General/Prime Contractor is the formal, documented process for resolving coordination issues between ICT work and other trades, because the GC/Prime is legally responsible for managing all subcontractors and trade sequencing on a…
Question
ICT project installation issues that require coordination with mechanical, electrical and/or other "trades" can be BEST accomplished by
Options
- Acoordinating with the job site supervisors
- Bissuing an RFI to the General/Prime Contractor
- Ctexting or calling the General/Prime Contractor
- Dissuing a Change Order
How the community answered
(52 responses)- A6% (3)
- B83% (43)
- C2% (1)
- D10% (5)
Explanation
Issuing an RFI (Request for Information) to the General/Prime Contractor is the formal, documented process for resolving coordination issues between ICT work and other trades, because the GC/Prime is legally responsible for managing all subcontractors and trade sequencing on a job site. A is wrong because job site supervisors lack the authority to formally direct other trade contractors or modify work scope. C is wrong because texting or calling is informal and creates no paper trail - verbal communication has no legal standing in construction disputes. D is wrong because a Change Order is used to modify contract scope, cost, or schedule, not to request coordination or clarification.
Memory tip: Think "RFI = Request For Information" - when you need answers or coordination before work proceeds, you request information through the proper chain. Change Orders come after decisions are made; RFIs help you make the decision in the first place.