RCDD-002 · Question #62

Which of the following options BEST describes Request for Quote (RFQ)?

The correct answer is A. Usually provides more detail involved with selecting the material, equipment, and components. Option A is correct because an RFQ (Request for Quote) is specifically used when the buyer already knows what they need and wants vendors to provide pricing for specific materials, equipment, or components - it requires detailed specifications so suppliers can give accurate…

ICT Design Fundamentals and Project Management

Question

Which of the following options BEST describes Request for Quote (RFQ)?

Options

  • AUsually provides more detail involved with selecting the material, equipment, and components
  • BCan be submitted by the contractor in response to a field order or as an uninitiated request for a
  • CUsed to obtain a formal response to the contract documents
  • DAn invitation for the design professionals (e g, architect, engineer, consultant) or contractors to

How the community answered

(30 responses)
  • A
    73% (22)
  • B
    3% (1)
  • C
    7% (2)
  • D
    17% (5)

Explanation

Option A is correct because an RFQ (Request for Quote) is specifically used when the buyer already knows what they need and wants vendors to provide pricing for specific materials, equipment, or components - it requires detailed specifications so suppliers can give accurate cost estimates.

Why the distractors are wrong:

  • B describes a Request for Information (RFI), which contractors submit to clarify ambiguities or request additional details from the design team.
  • C describes an Invitation to Bid (ITB) or Invitation for Bid, where contractors submit formal bids in response to complete contract documents.
  • D describes a Request for Proposal (RFP) or Request for Qualifications (RFQ/RFQ), which solicits design professionals or contractors to propose solutions or qualifications.

Memory tip: Think of RFQ as "Request for a Quote on what I already know I need" - the buyer has already defined the item; they just need the price. If you're comparing procurement documents, remember the spectrum: RFI (need info) → RFQ (need a price for known items) → RFP (need a full proposal/solution).

Topics

#RFQ#Procurement#Material selection#Bidding process