nerdexam
BICSI

RCDD-002 · Question #96

A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?

The correct answer is B. The component has met the quality requirements to meet program objectives. See the full explanation below for the reasoning.

Question

A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?

Options

  • AThe component has released resources to meet program objectives
  • BThe component has met the quality requirements to meet program objectives
  • CThe component has met the schedule requirements to meet program objectives
  • DThe component has met the benefits realization criteria to meet program objectives

How the community answered

(37 responses)
  • A
    11% (4)
  • B
    81% (30)
  • C
    3% (1)
  • D
    5% (2)

Community Discussion

No community discussion yet for this question.

Full RCDD-002 Practice