- Question #51
You selected the Standard Project Type as the most appropriate approach for successful implementation. Your team is engaged in the Analysis phase and they finished gathering the bu...
- Question #52
Your customer wants to ensure their business software does not contain undocumented code. What can you do to ensure your team will not deliver undocumented code?
- Question #53
The sales team wants to close the sales process. They need to make sure that the scope and all other recommendations for project execution are analyzed, documented, and agreed upon...
- Question #54
A prospective customer asks your sales person to prove that the proposed solution supports the specific industry requirements. You need to ensure due-diligence is achieved. What sh...
- Question #55
You need to map requirements in the Fit Gap Analysis Worksheet to appropriate categories to help scope the level of effort required. Which of the following categorizations provide...
- Question #56
You collaborated with the Solution Sales team to strategize how to execute a Business Case Assessment. Which customer benefits do you realize when you execute a Business Case Asses...
- Question #57
Your team started a pilot rollout scenario to implement and deploy a Microsoft Dynamics solution. You notice that the customer continually adjusts the solution and that the project...
- Question #58
Before executing a Requirements and Process Review Decision Accelerator, you need to gather data and document conditions. Which of the following are pre-conditions for this Decisio...
- Question #59
Your team needs to implement a Microsoft Dynamics solution for a large enterprise business that has complex business requirements and four globally distributed sites. Although each...
- Question #60
You are a consultant for a company. You need to review the scope of the implementation process. Which of the following activities are within the scope of the Requirements and Proce...
- Question #61
During conversations with the customer in the early sales stage, you discussed the current availability of compliant hardware and infrastructure at the customer site. You also lear...
- Question #62
You are creating a Project Charter. Which information should you include in this document? Choose the 3 that apply.
- Question #63
Your company's Sales Manager approaches you with an opportunity for selling a Microsoft Dynamics business solution. You are responsible for quickly finalizing the sale of the solut...
- Question #64
You are working to transition a large-scaled and complex company environment to a Microsoft Dynamics solution. Your team is currently focussed on deployment activities. You need to...
- Question #65
You are developing a strategy to implement quality requirements. The project is sized as a standard implementation that requires some customization. Which of the following tools sh...
- Question #66
You need to prepare to close a contract. What should you do? Choose the 2 that apply.
- Question #67
You and your team completed a successful deployment and Go-live cutover. In the first week following the Go-live cutover, your customer reports issues related to system setup and c...
- Question #68
Your team has successfully deployed a Microsoft Dynamics solution in a large global organization with multiple sites. Daily business transactions and activities are now operational...
- Question #69
Performance optimization tasks were executed in the operation phase. Which optimization tasks will you need to consider addressing in the future? Choose the 2 that apply.
- Question #70
You have successfully executed your project and the contract is formally closed. Are there any remaining tasks to complete?
- Question #71
You are a project manager, and you use Microsoft Dynamics Sure Step for implementations of Microsoft Dynamics products for your customers. Your customer's major stakeholders identi...
- Question #72
Which document should you use to manage project deliverables?
- Question #73
You are a project manager. You find that the personnel in the Human Resources department are new and not experienced in project work. You need to manage the project resources to ac...
- Question #74
You are a project manager, and you use Microsoft Dynamics Sure Step Methodology to manage projects. You need to ensure that quality assurance is part of a project that you are mana...
- Question #75
As a project manager, you need to incorporate a change request into the project. Which two tasks must be completed to correctly handle this request when you use the Microsoft Dynam...
- Question #76
Which activity is a precondition for communication management?
- Question #77
Which statement is an objective of solution envisioning?
- Question #78
You are performing a new Microsoft Dynamics GP implementation for a customer who has 10 users. The customer does not want to use customizations or independent software vendor (ISV)...
- Question #79
What is an objective of diagnostic preparation?
- Question #80
You are performing a Decision Accelerator Offering. In which order should you perform the steps?
- Question #81
Which two activities are included in the Diagnostic phase? (Each correct answer presents part of the solution. Choose two.)
- Question #82
Which two statements differentiating projects from operational work are correct? (Each correct answer presents part of the solution. Choose two.)
- Question #83
Which item is a project management process?
- Question #84
You are a project manager. You use the classic triple constraint model. If one constraint is changed, what happens to the other constraints?
- Question #85
You need to illustrate the dimensions of the project management diamond. Which dimension should you place at the center of the diamond?
- Question #86
You need to create 3 project management diamond. Which constraints should you use at each corner?
- Question #87
You are performing the solution envisioning process with a customer. The customer requests that you use all of the Decision Accelerator Offerings. What is the first step you should...
- Question #88
You must complete a Requirements and Process Review during an engagement. What should you identify and document at the completion of the exercise?
- Question #89
Which Decision Accelerator is a pre-condition for the Fit Gap and Solution Blueprint?
- Question #90
Which two categories should be used for requirements in the Fit Gap Analysis spreadsheet? (Each correct answer presents part of the solution. Choose two.)
- Question #91
Which project types does the Microsoft Dynamics Sure Step Model use?
- Question #92
You are responsible for creating and managing projects in a project repository. Which two actions can you perform on existing projects in the repository? (Each correct answer prese...
- Question #93
You need to create a project by using the Sure Step Project Creation Wizard. Which two properties must you identify in order to proceed? (Each correct answer presents part of the s...
- Question #94
As a project manager, you need to ascertain which human resources are involved in the project and Fit Gap documents on the Decision Accelerators. Which two Microsoft Dynamics Sure...
- Question #95
Which document is generated as a result of the functional requirements document (FRD)?
- Question #96
You are delivering a project by using the waterfall delivery method. You approve the project charter and project plan. Which three actions should you do next? (Each correct answer...
- Question #97
You are a project manager. You are running a project by using the waterfall delivery method. The project is in the development phase. Which Microsoft Dynamics Sure Step Methodology...
- Question #98
During which phase of a waterfall delivery is the creation and delivery of a complete system configuration performed?
- Question #99
You are a project manager. You are taking over a Microsoft Dynamics implementation. The project is in the design phase. You need to identify the test activities. Which two activiti...
- Question #100
Go live is complete, and you are now in the operation phase of the project, Which two activities can be performed in the operations phase? (Each correct answer presents part of the...