You are performing a new Microsoft Dynamics GP implementation for a customer who has 10 users. The customer does not want to use customizations or independent software vendor (ISV) solutions. Which…
The correct answer is A. rapid. Rapid Implementation: an accelerated approach for implementing Microsoft Dynamics with minimal or no customizations. This can be used in situations characterized by a limited scopewhere the basic application features are desired, and/or where the large majority of the…
Question
You are performing a new Microsoft Dynamics GP implementation for a customer who has 10 users. The customer does not want to use customizations or independent software vendor (ISV) solutions. Which project type should you use to deliver the implementation?
Options
- Arapid
- Bstandard
- Cagile
- Denterprise
How the community answered
(30 responses)- A70% (21)
- B7% (2)
- C7% (2)
- D17% (5)
Explanation
Rapid Implementation: an accelerated approach for implementing Microsoft Dynamics with minimal or no customizations. This can be used in situations characterized by a limited scopewhere the basic application features are desired, and/or where the large majority of the customer's business processes are not considered as complex. RAPID - a proven framework to accelerate and de-risk implementations by delivering standard deliverables out of the box cutting down the overall implementation time significantly. RAPID stands for Ready to use And Proven Implementation Deliverables.