The correct answer is B. identifying project stakeholders. See the full explanation below for the reasoning.

Question

Which activity is a precondition for communication management?

Options

  • Adefining project roles
  • Bidentifying project stakeholders
  • Canalyzing risk
  • Ddefining project scope