MB5-705 · Question #29
You are managing a Microsoft Dynamics implementation at a single site. The Analysis phase is completed and your application and technical consultants are now defining and documenting how to…
The correct answer is A. Create a deployment plan. B. Create a knowledge transfer plan. See the full explanation below for the reasoning.
Question
You are managing a Microsoft Dynamics implementation at a single site. The Analysis phase is completed and your application and technical consultants are now defining and documenting how to implement the business requirements. Which activities should you consider executing at this stage of the project? Choose the 2 that apply.
Options
- ACreate a deployment plan.
- BCreate a knowledge transfer plan.
- CDevelop a communications strategy plan.
- DFinalize and obtain customer sign-off of the technical architecture design.
How the community answered
(40 responses)- A73% (29)
- C10% (4)
- D18% (7)