MB5-705 · Question #28

You are engaged in a complex enterprise project environment. You need to ensure strict quality control. What should you do? Choose the 2 that apply.

The correct answer is A. Use the flowcharts that were analyzed and defined during the business process analysis phase to identify B. Use a cause and effect diagram to illustrate how various factors might be linked to potential effects. See the full explanation below for the reasoning.

Question

You are engaged in a complex enterprise project environment. You need to ensure strict quality control. What should you do? Choose the 2 that apply.

Options

  • AUse the flowcharts that were analyzed and defined during the business process analysis phase to identify
  • BUse a cause and effect diagram to illustrate how various factors might be linked to potential effects.
  • CUse the Role and Responsibilities template to map the project roles to specific people.
  • DUse the periodically structured and independently reviewed Optimization Offerings to identify inefficient