Which project types does the Microsoft Dynamics Sure Step Model use?
The correct answer is C. standard, rapid, enterprise, agile, and upgrade. The standard set of templates available using Microsoft Dynamics Sure Step Model is standard, rapid, enterprise and agile.
Initiate Microsoft Dynamics implementation projects
Question
Which project types does the Microsoft Dynamics Sure Step Model use?
Options
- Awaterfall, iterative
- Bdiagnostic, analysis, design, development, deployment, and operation
- Cstandard, rapid, enterprise, agile, and upgrade
- Ddiagnostic, development, and operational
How the community answered
(28 responses)- A14% (4)
- B7% (2)
- C75% (21)
- D4% (1)
Explanation
The standard set of templates available using Microsoft Dynamics Sure Step Model is standard, rapid, enterprise and agile.
Topics
#Sure Step project types#rapid#enterprise#agile upgrade