You complete diagnostic activities. You need to perform the proposal generation activity to summarize the findings. Which two documents should you create as part of the proposal generation activity?…

The correct answer is B. high-level project charter C. high-level project plan. Proposal Generation The key benefits gained by performing this activity are: - Development of the high-level Project Charter and Project Plan. - The documentation of conclusions and implementation proposal content. - The documentation of scope delimitations and risk assessments.

Initiate Microsoft Dynamics implementation projects

Question

You complete diagnostic activities. You need to perform the proposal generation activity to summarize the findings. Which two documents should you create as part of the proposal generation activity? (Each correct answer presents part of the solution. Choose two.)

Options

  • Astatement of work
  • Bhigh-level project charter
  • Chigh-level project plan
  • Dhigh-level budget proposal

How the community answered

(24 responses)
  • A
    8% (2)
  • B
    75% (18)
  • D
    17% (4)

Explanation

Proposal Generation The key benefits gained by performing this activity are: - Development of the high-level Project Charter and Project Plan. - The documentation of conclusions and implementation proposal content. - The documentation of scope delimitations and risk assessments.

Topics

#proposal generation#diagnostic activities#project charter#project plan