Which document is generated as a result of the functional requirements document (FRD)?

The correct answer is B. Fit Gap Analysis worksheet. See the full explanation below for the reasoning.

Question

Which document is generated as a result of the functional requirements document (FRD)?

Options

  • Asolution design document (SDD)
  • BFit Gap Analysis worksheet
  • Cfunctional design document (FDD)
  • Dtechnical design document (TDD)

How the community answered

(29 responses)
  • A
    14% (4)
  • B
    76% (22)
  • C
    3% (1)
  • D
    7% (2)