MB5-705 · Question #96
MB5-705 Question #96: Real Exam Question with Answer & Explanation
The correct answer is C. Perform and document the Fit Gap Analysis. E. Develop future state business process models. F. Conduct the Executive and Project Team kickoff meetings.. f789286a4f34/Fit_Gap_Datasheet.pdf
Question
You are delivering a project by using the waterfall delivery method. You approve the project charter and project plan. Which three actions should you do next? (Each correct answer presents part of the solution. Choose three.)
Exhibit
Options
- ADocument the configuration of the overall Microsoft Dynamics solution.
- BCreate the deployment plan.
- CPerform and document the Fit Gap Analysis.
- DComplete the design specifications.
- EDevelop future state business process models.
- FConduct the Executive and Project Team kickoff meetings.
Explanation
f789286a4f34/Fit_Gap_Datasheet.pdf