MB5-705 · Question #116
You are a project manager and you are using the waterfall delivery for a project. Which two items must be completed within the development phase? (Each correct answer presents part of the solution…
The correct answer is A. project design B. custom coding. The goal of the Development phase is to build and test the system components defined and approved in the design specifications, including developing the customizations, integrations and interfaces, and data migration processes. dev-in-a-waterfall-environment-quot-govdev.aspx
Execute Microsoft Dynamics implementation projects
Question
You are a project manager and you are using the waterfall delivery for a project. Which two items must be completed within the development phase? (Each correct answer presents part of the solution. Choose two.)
Exhibit
Options
- Aproject design
- Bcustom coding
- Canalysis phase
- Dproduction specifications
- Edesign phase
How the community answered
(48 responses)- A75% (36)
- C8% (4)
- D15% (7)
- E2% (1)
Explanation
- The goal of the Development phase is to build and test the system components defined and approved in the design specifications, including developing the customizations, integrations and interfaces, and data migration processes. dev-in-a-waterfall-environment-quot-govdev.aspx
Topics
#waterfall delivery#development phase#project phases#Sure Step methodology