MB5-705 · Question #110
Which two activities are specific to the agile project type? (Each correct answer presents part of the solution. Choose two.)
The correct answer is A. define solution backlog B. sprint configuration and development. A: Some Agile project type activities are performed against the Sprint Backlog, which is a compiled list of requirements from the Solution Backlog that is broken into smaller increments of product features. B: The Sure Step Agile project type has Sprint cycles to encompass the…
Question
Which two activities are specific to the agile project type? (Each correct answer presents part of the solution. Choose two.)
Options
- Adefine solution backlog
- Bsprint configuration and development
- Cgather development standards
- Dvalidate design security
How the community answered
(44 responses)- A80% (35)
- C7% (3)
- D14% (6)
Explanation
A: Some Agile project type activities are performed against the Sprint Backlog, which is a compiled list of requirements from the Solution Backlog that is broken into smaller increments of product features. B: The Sure Step Agile project type has Sprint cycles to encompass the Analysis, Design and Development phases. The Agile project type does have two phases, Deployment and Operation, at the culmination of the Spring cycles. implementation.aspx