MB5-705 · Question #85
You need to illustrate the dimensions of the project management diamond. Which dimension should you place at the center of the diamond?
The correct answer is D. expectations. Quality, time, cost and scope can be interpreted as project constraints.
Plan Microsoft Dynamics implementation projects
Question
You need to illustrate the dimensions of the project management diamond. Which dimension should you place at the center of the diamond?
Options
- Aquality
- Bcost
- Ctime
- Dexpectations
- Escope
How the community answered
(29 responses)- A7% (2)
- B3% (1)
- C3% (1)
- D86% (25)
Explanation
Quality, time, cost and scope can be interpreted as project constraints.
Topics
#project management diamond#expectations#triple constraint#project balance