You are a project manager. You find that the personnel in the Human Resources department are new and not experienced in project work. You need to manage the project resources to accommodate the lack…
The correct answer is A. Add more time for the project activities. See the full explanation below for the reasoning.
Question
You are a project manager. You find that the personnel in the Human Resources department are new and not experienced in project work. You need to manage the project resources to accommodate the lack of project experience in the project. What should you do?
Options
- AAdd more time for the project activities.
- BRelease the project team.
- CDocument the problem and the impact on the scope of the project to the major stakeholders.
- DDocument the impact of the lack of experience on the legal requirements.
How the community answered
(31 responses)- A77% (24)
- B6% (2)
- C13% (4)
- D3% (1)
Community Discussion