Question

You are working to transition a large-scaled and complex company environment to a Microsoft Dynamics solution. Your team is currently focussed on deployment activities. You need to make sure that proven cut over processes are in place to reduce the risks in the go- live period. Which key tasks should be included when planning for the Go-live cutover? Choose the 2 that apply.

Options

  • AWrite a Go-live cutover process document that defines the details of the cut-over plan on a step-by-step
  • BAt least two weeks before the final cut-over is due, run the full cut-over process as a dry run, against one
  • CProvide the appropriate level of end user training before Go-live.
  • DEnsure final resolution for all change requests and listed issues.