RCDD Exam Questions
371 real RCDD exam questions with expert-verified answers and explanations. Page 4 of 8.
- Question #151
Assume the following: - An equipment room (ER) consists of 16 racks arranged in 4 equal rows - The first 4 racks are numbered R1-1 though R1-4 - The second 4 racks are numbered R2-...
- Question #152
In an industry where a high level of humidity is measured, which type of label should be used?
- Question #153
What is the worst case acceptance value for attenuation when testing 2000 m (6562 ft) of 50/125 multimode fiber at a wavelength of 1300 nm when the fiber has 2 connector pairs and...
- Question #154
When balanced twisted-pair copper cabling, return loss is a measurement of the:
- Question #155
You are preparing to test newly installed open office cabling. Within the open office cabling, there are multiple consolidation points (CP) that were installed while waiting for fu...
- Question #156
You have been asked to test and troubleshoot an installed base of cabling that is believed to be causing network problems. You are finding that there are high levels of return loss...
- Question #157
Premises optical fiber links should be tested:
- Question #158
The diagram below is a typical configuration for:
- Question #159
Where backbone cabling exceeds cabling lengths for the same performance or design (for product used in horizontal cabling), there are three fundamental tests which should be consid...
- Question #160
A scope of work should contain all of the following EXCEPT:
- Question #161
What is the PERT estimate of time for cable placement on a given job? - Optimistic time is 100 hours - Most likely time is 125 hours - Pessimistic time is 210 hours
- Question #162
At the end of the third week of a project, the actual cost of work performed is $7000 USd and the budgeted cost of work performed is $8000 USd. Which of the following is true?
- Question #163
The figure below represents what type of chart?
- Question #164
At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?
- Question #165
Select the appropriate task to complete section 2.2 of the work breakdown structure (WBS) below: 2 Technician 2.1 Install cabling 2.2 __________ 2.3 Activate wireless
- Question #166
All of the following are true about the post construction phase EXCEPT:
- Question #167
Which area of project management covers the blending of various subteams into a project organization with a cohesive plan?
- Question #168
When developing a safety plan, consider all of the following EXCEPT:
- Question #169
Select the appropriate task to complete the section 2.2 of the work breakdown structure below: 2. Technician 2.1 Install rack 2.2 _________ 2.3 Place fiber 2.4 Terminate fiber 2.5...
- Question #170
Which of the following does NOT describe one of the four main types of specifications?
- Question #171
Which is NOT a type of contract?
- Question #172
If a work breakdown structure (WBS) shows the tasks below, what is C, the successor task?
- Question #173
Which is NOT true about conformance quality?
- Question #174
What is the PERT estimate (in hours) for project design where: - Optimistic time is 40 hours - Most likely time is 50 hours - Pessimistic time is 60 hours
- Question #175
All of the following are considered market or regional conditions that can impact construction costs EXCEPT:
- Question #176
What type of estimate is based on the cost of performing similar work in the past, adjusted for current job conditions?
- Question #177
A work breakdown structure is:
- Question #178
A building has six floors plus a basement. Each floor is 10,000 square feet and has approximately 50 CATV outlets respectively. There is a single hardline trunk cable installed fro...
- Question #179
Which of the following is NOT an element of a cable system?
- Question #180
An active video converter is used in what type of CATV cable distribution system?
- Question #181
A building has a series of CATV outlets each with cables installed back to a telecommunications room (TR), and each telecommunications room (TR) is connected to the headend. What i...
- Question #182
What is the appropriate impedance of coaxial cable for use with broadband distribution?
- Question #183
Active video converters are required for what type of CATV distribution system?
- Question #184
The following diagram indicates what type of CATV distribution system?
- Question #185
The headend has several modulators assigning frequencies for distribution to the CATV network. What distribution device should you use immediately at the headend to distribute the...
- Question #186
The following diagram represents what type of CATV distribution system?
- Question #187
A building has six floors plus a basement. Each floor is 10,000 square feet and has approximately 50 CATV outlets respectively. There is a single hardline trunk cable installed fro...
- Question #188
The headend has several audio-video playback devices within it. What piece of equipment is required to assign their output signals to specific RF carriers on the CATV system?
- Question #189
A building has six floors plus a basement. Each floor is 929 sq m (10,000 sq ft) and has approximately 50 CATV outlets respectively. There is a single hardline trunk cable installe...
- Question #190
You are designing a building with a combination of Class A commercial office spaces and residences. The design program requires having unlimited cable channels available at all out...
- Question #191
What element is typically NOT part of a paging system?
- Question #192
A properly designed distributed paging system will provide a sound pressure level (SPL) for audio paging that is between ________ above ambient noise level.
- Question #193
You are designing a four story retail mall and multiple sound systems within it. Which system should you design to support general music programming within common retail areas?
- Question #194
For design purposes, loudspeakers are rated for a measured sound pressure level (SPL) at:
- Question #195
You are designing a paging system for a 588 sq m (6325 sq ft) open office space. Due to architectural features of the ceiling, wall mounted speakers must be used. Following the gen...
- Question #196
What is the recommended distance between ceiling mounted speakers in a hallway with heavy traffic?
- Question #197
A space has all hard surfaces including architecture and furnishings. The audio programming produced from the distributed sound system has become unintelligible. Which of the follo...
- Question #198
Using the sound pressure level (SPL) method of approximating distance and power, calculate the power required to produce 89 dB at 4 m (13.1 ft) with a loud speaker that is rated at...
- Question #199
In a hallway with normal traffic, ceiling mounted speakers should be placed ________ times the corridor height, minus the ________.
- Question #200
You are designing a restaurant located within a retail mall. The ambient noise level of the restaurant is 70 dB. The ambient noise level of the mall common space is 75 dB. What is...