nerdexam
BICSI

RCDD · Question #176

What type of estimate is based on the cost of performing similar work in the past, adjusted for current job conditions?

The correct answer is A. Analogous. Analogous estimating uses actual costs from past similar projects as a baseline, then adjusts that figure for the current project's scope and conditions.

Design, Implementation, and Management

Question

What type of estimate is based on the cost of performing similar work in the past, adjusted for current job conditions?

Options

  • AAnalogous
  • BParametric
  • CEngineering
  • DLedger
  • EPERT

How the community answered

(51 responses)
  • A
    75% (38)
  • B
    6% (3)
  • C
    2% (1)
  • D
    4% (2)
  • E
    14% (7)

Why each option

Analogous estimating uses actual costs from past similar projects as a baseline, then adjusts that figure for the current project's scope and conditions.

AAnalogousCorrect

Analogous estimating, also called top-down estimating, directly leverages historical cost data from comparable completed projects as its primary input. It then scales and adjusts that historical figure based on differences in size, complexity, and current market conditions, making it faster to produce but less precise than detailed bottom-up estimating methods.

BParametric

Parametric estimating uses statistical unit-rate relationships such as cost per square foot or cost per unit rather than direct comparison to a single historical project's total cost.

CEngineering

Engineering or bottom-up estimating builds cost from detailed quantity takeoffs and applied unit prices, not from an overall historical project cost comparison.

DLedger

Ledger estimating is not a recognized standard estimating methodology in project management or construction cost engineering practice.

EPERT

PERT is a three-point technique used for schedule duration estimation, not for deriving cost estimates from past similar project data.

Concept tested: Analogous cost estimating using historical project data

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok-guide

Topics

#analogous estimating#cost estimation#historical data#estimate types

Community Discussion

No community discussion yet for this question.

Full RCDD Practice