RCDD · Question #176
What type of estimate is based on the cost of performing similar work in the past, adjusted for current job conditions?
The correct answer is A. Analogous. Analogous estimating uses actual costs from past similar projects as a baseline, then adjusts that figure for the current project's scope and conditions.
Question
What type of estimate is based on the cost of performing similar work in the past, adjusted for current job conditions?
Options
- AAnalogous
- BParametric
- CEngineering
- DLedger
- EPERT
How the community answered
(51 responses)- A75% (38)
- B6% (3)
- C2% (1)
- D4% (2)
- E14% (7)
Why each option
Analogous estimating uses actual costs from past similar projects as a baseline, then adjusts that figure for the current project's scope and conditions.
Analogous estimating, also called top-down estimating, directly leverages historical cost data from comparable completed projects as its primary input. It then scales and adjusts that historical figure based on differences in size, complexity, and current market conditions, making it faster to produce but less precise than detailed bottom-up estimating methods.
Parametric estimating uses statistical unit-rate relationships such as cost per square foot or cost per unit rather than direct comparison to a single historical project's total cost.
Engineering or bottom-up estimating builds cost from detailed quantity takeoffs and applied unit prices, not from an overall historical project cost comparison.
Ledger estimating is not a recognized standard estimating methodology in project management or construction cost engineering practice.
PERT is a three-point technique used for schedule duration estimation, not for deriving cost estimates from past similar project data.
Concept tested: Analogous cost estimating using historical project data
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok-guide
Topics
Community Discussion
No community discussion yet for this question.