RCDD · Question #168

When developing a safety plan, consider all of the following EXCEPT:

The correct answer is A. Safety may be excluded from scope where an information technology system (ITS) designer is. Safety cannot be excluded from project scope based on the type of designer involved - it is a mandatory planning requirement for all project types including ITS projects.

Design, Implementation, and Management

Question

When developing a safety plan, consider all of the following EXCEPT:

Options

  • ASafety may be excluded from scope where an information technology system (ITS) designer is
  • BAreas that should be addressed by the safety plan include emergency numbers and work area
  • CThe safety coordinator should hold a safety meeting prior to the start of the project
  • DThe contractor should contact the customer safety coordinator to evaluate site specific emergency

How the community answered

(51 responses)
  • A
    82% (42)
  • B
    4% (2)
  • C
    12% (6)
  • D
    2% (1)

Why each option

Safety cannot be excluded from project scope based on the type of designer involved - it is a mandatory planning requirement for all project types including ITS projects.

ASafety may be excluded from scope where an information technology system (ITS) designer isCorrect

This statement is false and is therefore the correct answer to an EXCEPT question. Safety is never permitted to be excluded from scope simply because an information technology system (ITS) designer is the lead. All projects, regardless of technical discipline, require a safety plan, and the ITS designer context does not create an exception to this requirement.

BAreas that should be addressed by the safety plan include emergency numbers and work area

Including emergency contact numbers and work area safety considerations in a safety plan is a true and standard requirement, so this is not the exception.

CThe safety coordinator should hold a safety meeting prior to the start of the project

Having the safety coordinator hold a pre-project safety meeting is a true and widely accepted safety planning best practice, so this statement is accurate.

DThe contractor should contact the customer safety coordinator to evaluate site specific emergency

The contractor contacting the customer's safety coordinator to evaluate site-specific emergency procedures is a true and standard safety coordination responsibility.

Concept tested: Safety plan scope requirements for ITS projects

Topics

#safety plan#construction safety#project management#emergency procedures