You have been selected to do the telecommunications design on a new, single story building. The architect requires the size and location of the telecommunications rooms so their building design can…

The correct answer is B. Determine the number of , their locations, and telecommunications services needed. Identifying the number and location of work areas and the telecommunications services they require is the logical first step because it directly determines the size, quantity, and placement of telecommunications rooms needed by the architect.

Design, Implementation, and Management

Question

You have been selected to do the telecommunications design on a new, single story building. The architect requires the size and location of the telecommunications rooms so their building design can proceed. From the items listed below (all of which are required for the design), which one is the logical starting point in order to provide the architect with a size and location for the room?

Options

  • ADetermine where the entrance facility will be
  • BDetermine the number of , their locations, and telecommunications services needed
  • CDetermine the power, HVAC, electrical, and security requirements for the room
  • DDetermine future growth and other requirements
  • EDetermine the types of equipment to be installed in the room

How the community answered

(19 responses)
  • B
    79% (15)
  • C
    5% (1)
  • D
    11% (2)
  • E
    5% (1)

Why each option

Identifying the number and location of work areas and the telecommunications services they require is the logical first step because it directly determines the size, quantity, and placement of telecommunications rooms needed by the architect.

ADetermine where the entrance facility will be

The entrance facility location is determined after TR requirements are established, since TR placement drives where backbone cabling and entrance pathways must connect.

BDetermine the number of , their locations, and telecommunications services neededCorrect

The number of work areas, their locations, and the services they require directly drive the quantity, size, and placement of telecommunications rooms - precisely the information the architect needs to proceed. Without this foundational data, decisions about entrance facility routing, room power and HVAC loads, equipment selection, and growth planning have no technical basis. This step establishes the demand from which all other design decisions are derived.

CDetermine the power, HVAC, electrical, and security requirements for the room

Power, HVAC, and security requirements for the room cannot be properly specified until the room size and equipment loads are known, which first requires knowing the work area count and services.

DDetermine future growth and other requirements

Future growth planning is an important input but is secondary to establishing the baseline work area count and service requirements that define the core room design.

EDetermine the types of equipment to be installed in the room

Equipment type selection depends on the services and user counts determined by the work area survey, so this step logically follows choice B rather than preceding it.

Concept tested: Telecommunications room design logical starting point