RCDD · Question #174

What is the PERT estimate (in hours) for project design where: - Optimistic time is 40 hours - Most likely time is 50 hours - Pessimistic time is 60 hours

The correct answer is C. 50 hours. The PERT formula - (Optimistic + 4 x Most Likely + Pessimistic) / 6 - yields (40 + 200 + 60) / 6 = 50 hours.

Design, Implementation, and Management

Question

What is the PERT estimate (in hours) for project design where:

  • Optimistic time is 40 hours
  • Most likely time is 50 hours
  • Pessimistic time is 60 hours

Options

  • A40 hours
  • B45 hours
  • C50 hours
  • D55 hours
  • E60 hours

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    73% (27)
  • D
    16% (6)
  • E
    5% (2)

Why each option

The PERT formula - (Optimistic + 4 x Most Likely + Pessimistic) / 6 - yields (40 + 200 + 60) / 6 = 50 hours.

A40 hours

40 hours is only the optimistic estimate; it ignores the most likely and pessimistic values entirely and is not a weighted average.

B45 hours

45 hours does not result from the standard PERT three-point estimation formula applied to these inputs.

C50 hoursCorrect

Applying the PERT formula: (40 + 4x50 + 60) / 6 = 300 / 6 = 50 hours. The formula weights the most likely estimate four times more heavily than the optimistic and pessimistic values to reflect its higher probability of occurrence, resulting in a weighted average of 50 hours.

D55 hours

55 hours does not result from the standard PERT three-point estimation formula applied to these inputs.

E60 hours

60 hours is only the pessimistic estimate; it ignores the optimistic and most likely values entirely and is not a weighted average.

Concept tested: PERT three-point duration estimation formula

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok-guide

Topics

#PERT estimate#three-point estimation#project scheduling#time estimation