RCDD · Question #165
Select the appropriate task to complete section 2.2 of the work breakdown structure (WBS) below: 2 Technician 2.1 Install cabling 2.2 __________ 2.3 Activate wireless
The correct answer is A. Install access point. In a WBS for wireless network installation, tasks must follow a logical sequence - hardware must be physically installed before it can be configured or activated.
Question
Select the appropriate task to complete section 2.2 of the work breakdown structure (WBS) below:
2 Technician 2.1 Install cabling 2.2 __________ 2.3 Activate wireless
Options
- AInstall access point
- BClean work area
- CInstall pathway for cabling
- DConfirm wireless coverage
How the community answered
(41 responses)- A78% (32)
- B2% (1)
- C7% (3)
- D12% (5)
Why each option
In a WBS for wireless network installation, tasks must follow a logical sequence - hardware must be physically installed before it can be configured or activated.
Installing the access point is the logical intermediate step between running cabling (2.1) and activating wireless (2.3). The access point must be physically mounted and connected to the installed cabling before any wireless configuration or activation can occur. This makes it the only technically valid task to occupy section 2.2 in this sequence.
Cleaning the work area is a housekeeping task unrelated to the technical workflow sequence between cabling installation and wireless activation.
Installing pathway for cabling would logically precede cabling installation (2.1), not follow it, so it cannot fit between 2.1 and 2.3.
Confirming wireless coverage is a post-activation verification step that would occur after 2.3 (Activate wireless), not before it.
Concept tested: WBS task sequencing for wireless network installation