nerdexam
BICSI

RCDD · Question #164

At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?

The correct answer is A. The project is ahead of schedule. Schedule Variance (EV minus PV) determines whether a project is ahead of or behind its planned schedule at a given point in time.

Design, Implementation, and Management

Question

At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?

Options

  • AThe project is ahead of schedule.
  • BThe project is over budget.
  • CThe project is behind schedule.
  • DThe project is under budget.

How the community answered

(27 responses)
  • A
    74% (20)
  • B
    15% (4)
  • C
    7% (2)
  • D
    4% (1)

Why each option

Schedule Variance (EV minus PV) determines whether a project is ahead of or behind its planned schedule at a given point in time.

AThe project is ahead of schedule.Correct

Schedule Variance (SV) = Earned Value (EV) - Planned Value (PV) = $8000 - $7000 = +$1000. A positive SV means more work has been completed than was planned for this point in time, so the project is ahead of schedule. This is a core EVM schedule performance metric distinct from cost performance.

BThe project is over budget.

Over budget is a cost performance determination requiring Actual Cost (AC) data; no AC value is provided here, and PV vs EV does not measure budget status.

CThe project is behind schedule.

Behind schedule requires a negative SV where PV exceeds EV; here EV ($8000) is greater than PV ($7000), producing a positive variance indicating the opposite.

DThe project is under budget.

Under budget is determined by comparing EV to AC, not EV to PV; schedule variance cannot indicate budget status without actual cost data.

Concept tested: EVM schedule variance calculation and interpretation

Source: https://www.pmi.org/learning/library/earned-value-management-systems-analysis-8026

Topics

#earned value management#schedule variance#planned value#EV vs PV

Community Discussion

No community discussion yet for this question.

Full RCDD Practice