BICSI
RCDD · Question #164
RCDD Question #164: Real Exam Question with Answer & Explanation
The correct answer is A. The project is ahead of schedule.. Schedule Variance (EV minus PV) determines whether a project is ahead of or behind its planned schedule at a given point in time.
Question
At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?
Options
- AThe project is ahead of schedule.
- BThe project is over budget.
- CThe project is behind schedule.
- DThe project is under budget.
Explanation
Schedule Variance (EV minus PV) determines whether a project is ahead of or behind its planned schedule at a given point in time.
Common mistakes.
- B. Over budget is a cost performance determination requiring Actual Cost (AC) data; no AC value is provided here, and PV vs EV does not measure budget status.
- C. Behind schedule requires a negative SV where PV exceeds EV; here EV ($8000) is greater than PV ($7000), producing a positive variance indicating the opposite.
- D. Under budget is determined by comparing EV to AC, not EV to PV; schedule variance cannot indicate budget status without actual cost data.
Concept tested. EVM schedule variance calculation and interpretation
Reference. https://www.pmi.org/learning/library/earned-value-management-systems-analysis-8026
Community Discussion
No community discussion yet for this question.