nerdexam
BICSI

RCDD · Question #162

At the end of the third week of a project, the actual cost of work performed is $7000 USd and the budgeted cost of work performed is $8000 USd. Which of the following is true?

The correct answer is A. The project is under budget.. Earned Value Management uses Cost Variance (EV minus AC) to determine whether a project is over or under budget.

Design, Implementation, and Management

Question

At the end of the third week of a project, the actual cost of work performed is $7000 USd and the budgeted cost of work performed is $8000 USd. Which of the following is true?

Options

  • AThe project is under budget.
  • BThe project is budget incorrect.
  • CThe project has been back-end loaded.
  • DThe project is over budget.

How the community answered

(32 responses)
  • A
    84% (27)
  • B
    3% (1)
  • C
    9% (3)
  • D
    3% (1)

Why each option

Earned Value Management uses Cost Variance (EV minus AC) to determine whether a project is over or under budget.

AThe project is under budget.Correct

Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC) = $8000 - $7000 = +$1000. A positive CV indicates the project accomplished the planned work for less money than budgeted, meaning the project is under budget. This is a core EVM cost performance metric.

BThe project is budget incorrect.

'Budget incorrect' is not a valid EVM status designation; cost variance is a precise numerical result, not a qualitative judgment about budgeting errors.

CThe project has been back-end loaded.

Back-end loading refers to scheduling more work or cost toward the end of a project timeline, which cannot be determined from a single-point cost variance snapshot.

DThe project is over budget.

Over budget requires a negative CV where AC exceeds EV; here AC ($7000) is less than EV ($8000), producing a positive variance indicating the opposite.

Concept tested: EVM cost variance calculation and interpretation

Source: https://www.pmi.org/learning/library/earned-value-management-systems-analysis-8026

Topics

#earned value management#cost variance#budget performance#ACWP

Community Discussion

No community discussion yet for this question.

Full RCDD Practice