nerdexam
BICSI

RCDD · Question #161

What is the PERT estimate of time for cable placement on a given job? - Optimistic time is 100 hours - Most likely time is 125 hours - Pessimistic time is 210 hours

The correct answer is C. 135 hours. The PERT formula calculates a weighted average of three time estimates, giving the most likely estimate four times the weight of the others.

Design, Implementation, and Management

Question

What is the PERT estimate of time for cable placement on a given job?

  • Optimistic time is 100 hours
  • Most likely time is 125 hours
  • Pessimistic time is 210 hours

Options

  • A100 hours
  • B125 hours
  • C135 hours
  • D155 hours
  • E175 hours

How the community answered

(43 responses)
  • A
    7% (3)
  • B
    14% (6)
  • C
    74% (32)
  • D
    2% (1)
  • E
    2% (1)

Why each option

The PERT formula calculates a weighted average of three time estimates, giving the most likely estimate four times the weight of the others.

A100 hours

100 hours is only the optimistic estimate and does not apply the PERT weighted average formula across all three time values.

B125 hours

125 hours is only the most likely estimate and ignores the pessimistic value entirely, which is not the PERT calculation.

C135 hoursCorrect

The PERT formula is (Optimistic + 4 x Most Likely + Pessimistic) / 6. Substituting the given values: (100 + 4x125 + 210) / 6 = (100 + 500 + 210) / 6 = 810 / 6 = 135 hours. The fourfold weighting on the most likely estimate reflects its statistically higher probability of occurrence.

D155 hours

155 hours results from a simple unweighted arithmetic mean of the three values, which is not the PERT formula.

E175 hours

175 hours is not produced by the PERT formula under any standard interpretation of these three inputs.

Concept tested: PERT three-point weighted average time estimation

Source: https://www.pmi.org/learning/library/three-point-estimating-techniques-6683

Topics

#PERT#time estimation#project scheduling#weighted average

Community Discussion

No community discussion yet for this question.

Full RCDD Practice