- Question #102
Which process examines methods, techniques, and principles from peer organizations?
- Question #103
A customer wants to set up a new digital classroom and has approached the integrator for a quote. What is the BEST way to understand the customer's needs before creating the quote?
- Question #104
Which of the following is the BEST placement for studio monitor loudspeakers in a 4 m x 6 m room from an acoustic standpoint?
- Question #105
The amount of light emitted through a projection system lens is TYPICALLY specified and measured
- Question #106
If content is protected, the HDCP handshake(s) occurs
- Question #107
Noting the position of ventilation ducts is useful when determining
- Question #108
A cardioid subwoofer array uses delay, equalization, and
- Question #109
When selling rental or staging services, which is the MOST effective way to showcase a company's services and expertise?
- Question #110
Which of the following is a MAJOR consideration for implementing AVoIP?
- Question #111
By code, projection screens should be positioned in a manner that avoids blocking
- Question #112
What should be used to clean foam microphone wind screens?
- Question #113
When training a new user to operate the solution that has been provided, how should the training be started?
- Question #114
Which of these symbols is generally used to represent a network?
- Question #115
As a project manager, daily or weekly updates from the____are MOST USEFUL when trying to make sure a job comes in on time and on budget.
- Question #116
When the customer says: "The PA is only for speech reinforcement!", which of the following pieces of equipment is most likely NOT needed?
- Question #117
A personnel change at an AV integration company results in the assignment of a new technician to an existing facility. What is the best FIRST step for the integrator to make the tr...
- Question #118
A customer wants to reuse existing network cabling to extend audio and video signals in a system refresh. What is the PRIMARY concern?
- Question #119
During an initial meeting with a prospective client regarding an audiovisual project, it is important to understand the customer's method of procurement in order to avoid.
- Question #120
The bending or changing direction of a light ray as it passes through material is called
- Question #121
During a site survey, a client states that there will be no acoustical treatment to their new council chamber and they want a voice lifting (reinforcement) system. Which loudspeake...
- Question #122
In order to calculate throw distances for an existing installation, what is the FIRST thing to evaluate?
- Question #123
The MOST important information to come away with from an initial site survey is the
- Question #124
The purchaser in an AV solutions firm has a key role to play in the area of
- Question #125
What should be identified during a project's needs analysis?
- Question #126
One way to safeguard individual pieces of equipment in a rack from theft is the use of
- Question #127
According to the AVIXA Rack Design standard, what should be the MINIMUM distance between an AC Power cable and a Data Twisted Pair cable?
- Question #128
What is a common vulnerability in a networked AV System?
- Question #129
Invoicing clients, purchasing AV equipment and providing estimates are examples of which of the following types of work?
- Question #130
During the installation of an audiovisual system, a client states that they wish to add a videoconferencing system that was not considered in the initial scope of the project. What...
- Question #131
A schedule is being created for a project. Which of these factors will have the MOST impact on the calculations?
- Question #132
While conducting routine maintenance, an AV technician notices that there is distortion coming from the main loudspeaker. This is likely caused because the amplifier's
- Question #133
When should preventive maintenance be undertaken?
- Question #134
When responding to a potential client who quotes online pricing of a display from a retail store as a benchmark for expected pricing, how can the technician BEST counter their poin...
- Question #135
Which of the following takes the highest precedence when the interpretations of applicable codes and standards are in conflict?
- Question #136
Which of the following is an example of PPE?
- Question #137
A single panel in a large video wall is flickering. Where should the technician begin troubleshooting?
- Question #138
The FIRST step in troubleshooting an AV system is to
- Question #139
In the scope of work (SOW), an interface is described as being installed in the lectern. While the work is underway onsite, the client asks for the interface to be moved to a table...
- Question #140
Which is the MOST important factor during the development of an AV project scope?
- Question #141
What does a compressor control in an audio system?
- Question #142
When planning video content with a client, it is important to get their Pantone data (PMS) to ensure
- Question #143
Owner standards and design manuals are examples of which kind of documentation?
- Question #144
Given this system information: What is the MINIMUM current requirement (assuming 110VAC electrical supply)?
- Question #146
The architect states that the project is in the pre-design phase. This would indicate that
- Question #147
Two computers are connected to a videoconferencing system through a switcher using HDMI cables. Computer content from PC A is being properly transmitted. However, when PC B is sele...
- Question #148
A client has a room that can be used as one large room or three separate rooms. Each room has several different audio and video options. What type of system should be suggested to...
- Question #149
Constant voltage distributed audio systems utilize a_____wiring scheme.
- Question #150
A university has equipped all of its theatres with laser projectors. The maintenance department should schedule
- Question #151
A client requests for a project to be completed earlier than initially scheduled. What should the AV contractor do FIRST to address this change?
- Question #152
A client wants a third-party commitment that a project will be completed as per contract and protection against losses if it is not. What document should they request from their su...