Avixa
CTS · Question #125
What should be identified during a project's needs analysis?
The correct answer is B. stakeholders involved. See the full explanation below for the reasoning.
Question
What should be identified during a project's needs analysis?
Options
- Athe overall budget
- Bstakeholders involved
- Cthe timeline for completion
- Dkey activities to be performed
How the community answered
(62 responses)- A3% (2)
- B77% (48)
- C13% (8)
- D6% (4)
Community Discussion