Which is the MOST important factor during the development of an AV project scope?
The correct answer is D. stakeholders requirements. See the full explanation below for the reasoning.
Question
Which is the MOST important factor during the development of an AV project scope?
Options
- Aentire budget
- Bclients responsibility
- Canalyze the strategic plan
- Dstakeholders requirements
How the community answered
(56 responses)- A11% (6)
- B5% (3)
- C2% (1)
- D82% (46)