nerdexam
Avixa

CTS · Question #139

CTS Question #139: Real Exam Question with Answer & Explanation

The correct answer is A. Advise the project manager of the request.. See the full explanation below for the reasoning.

Question

In the scope of work (SOW), an interface is described as being installed in the lectern. While the work is underway onsite, the client asks for the interface to be moved to a table next to the lectern. What is the proper response from the technician?

Options

  • AAdvise the project manager of the request.
  • BFollow the direction of the client, making a note in the job diary.
  • CFollow the direction of the client and advise the project manager of the change.
  • DAdvise the client that moving the interface is out of the scope and install the interface in the

Community Discussion

No community discussion yet for this question.

Full CTS Practice