A client requests for a project to be completed earlier than initially scheduled. What should the AV contractor do FIRST to address this change?
The correct answer is C. provide a request for change (RFC) to the client to approve the change to the schedule. See the full explanation below for the reasoning.
AV Installation
Question
A client requests for a project to be completed earlier than initially scheduled. What should the AV contractor do FIRST to address this change?
Options
- Adeny the request and work to the original agreed schedule
- Ballocate more resources to meet the earlier completion date
- Cprovide a request for change (RFC) to the client to approve the change to the schedule
- Dprovide a change order (CO) to the client outlining changes to the project and any additional costs
How the community answered
(44 responses)- A14% (6)
- B5% (2)
- C77% (34)
- D5% (2)
Topics
#change management#request for change#project schedule#change order