CTS · Question #151

A client requests for a project to be completed earlier than initially scheduled. What should the AV contractor do FIRST to address this change?

The correct answer is C. provide a request for change (RFC) to the client to approve the change to the schedule. See the full explanation below for the reasoning.

AV Installation

Question

A client requests for a project to be completed earlier than initially scheduled. What should the AV contractor do FIRST to address this change?

Options

  • Adeny the request and work to the original agreed schedule
  • Ballocate more resources to meet the earlier completion date
  • Cprovide a request for change (RFC) to the client to approve the change to the schedule
  • Dprovide a change order (CO) to the client outlining changes to the project and any additional costs

How the community answered

(44 responses)
  • A
    14% (6)
  • B
    5% (2)
  • C
    77% (34)
  • D
    5% (2)

Topics

#change management#request for change#project schedule#change order