Question

A client requests for a project to be completed earlier than initially scheduled. What should the AV contractor do FIRST to address this change?

Options

  • Adeny the request and work to the original agreed schedule
  • Ballocate more resources to meet the earlier completion date
  • Cprovide a request for change (RFC) to the client to approve the change to the schedule
  • Dprovide a change order (CO) to the client outlining changes to the project and any additional costs